Fort Stockton Plant
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Pecos County. First named in the release with data as of June 1, 2018.
Pecoscounty as printed
138kV
AEP TNCutility
3projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Pecos, TX: ERCOT queue, 58 active of 63. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Fort Stockton Plant: Rebuild 138/69 kV Station Rebuild the Fort Stockton Plant 138/69 kV station ERCOT project 80907 · RPG 25RPG032 |
AEP TNC Tier 3 |
Planned Future tab |
138 | Apr 2028 | Fort Stockton Plant Pecos County |
Fort Stockton Plant |
| Fort Stockton Plant to Lynx: Rebuild 138 kV Line Rehab the Fort Stockton Plant to Lynx 138 kV line ERCOT project 86829 · RPG 23RPG008 |
AEP TNC Tier 4 |
Planned Future tab |
138 | May 2028 | Fort Stockton Plant to Lynx Pecos County |
Fort Stockton Plant, Lynx |
| Fort Stockton Plant to Solstice: Rebuild 138 kV Line Rebuild the Fort Stockton Plant to Solstice 138 kV line and retire the PST at Solstice ERCOT project 91853 · utility no. TP2025145 · RPG H.B. 5066 |
AEP TNC Tier 3 |
Planned Future tab |
138 | Nov 2028 | Fort Stockton Plant to Solstice Pecos County |
Fort Stockton Plant, Solstice |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 80907 | Projected in-service date | Nov 2027 → Apr 2028 |
| October 1, 2026 | 91853 | Projected in-service date | Nov 2029 → Nov 2028 |
| February 1, 2026 | 80907 | Projected in-service date | May 2027 → Nov 2027 |
| February 1, 2026 | 86829 | Projected in-service date | Jan 2027 → May 2028 |
| February 1, 2026 | 91853 | Projected in-service date | Dec 2030 → Nov 2029 |
| October 1, 2025 | 80907 | Projected in-service date | Jan 2027 → May 2027 |
| June 1, 2025 | 80907 | Projected in-service date | Nov 2026 → Jan 2027 |
| June 1, 2025 | 91853 | First listed | on the Future tab |
| February 1, 2025 | 86829 | Projected in-service date | Sep 2026 → Jan 2027 |
| October 1, 2024 | 80907 | Projected in-service date | May 2026 → Nov 2026 |
| October 1, 2024 | 86829 | First listed | on the Future tab |
| June 1, 2024 | 80907 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.