Substation Scout

Jewett

Named in 6 listed projects in ERCOT’s transmission project tracking workbook, in Leon County. First named in the release with data as of February 1, 2015.

Leoncounty as printed
138, 345kV
CNP, ONCORutility
6projects listed

Also printed as: Jewett Switch

A HIFLD substation record has the same name and county: JEWETT (LEON County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Leon, TX: ERCOT queue, 13 active of 14. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Install Jewett Switch - Crockett Switch 138 kV Line Ckt #2
ERCOT project 110000 · utility no. R6554
ONCOR
Tier 1
Conceptual
Future tab
138 May 2030 Jewett Switch to Crockett Switch
Leon / Houston County
Jewett Switch, Crockett Switch
Jewett Switch - Greene Switch 345 kV Double-Circuit Line
Establish Jewett Switch - Greene Switch 345 kV Double-Circuit Line
ERCOT project 110381 · utility no. M4428 · RPG 25RPG042 · RTP 2024-NC63
ONCOR
Tier 1
Planned
Future tab
345 May 2033 Greene Switch to Jewett Switch
Dallas / Leon County
Greene Switch, Jewett Switch
Newby (NBY) CEHE-Owned 345 kV Substation for DEWEY (DWY) / Jewett Energy Center (29INR0150)
Loop new Newby (NBY) 345kV CEHE Substation into Ckt.74 to create new Ckt.74 Jewett to Newby to Limestone. Install (1) 6-Ohm reactor at Newby substation in-series with Ckt.74 Newby to Limestone.
ERCOT project 111258A
CNP
Tier 4
Planned
Future tab
345 Oct 2028 Newby to Jewett / Limestone
Freestone / Leon County
Newby, Jewett, Limestone
Newby (NBY) CEHE-Owned 345 kV Substation for DEWEY (DWY) / Jewett Energy Center (29INR0150)
Loop new Newby (NBY) 345kV CEHE Substation into Ckt.98 to create new Ckt.98 Limestone to Newby to Jewett. Install (1) 6-Ohm reactor at Newby substation in-series with Ckt.98 Newby to Limestone.
ERCOT project 111258B
CNP
Tier 4
Planned
Future tab
345 Oct 2028 Newby to Limestone / Jewett
Freestone / Leon County
Newby, Limestone, Jewett
Install new Skains (SKA) 345kV Substation for generator interconnection to Hollow Branch Creek Solar (24INR0422)
Install new Skains (SKA) 345kV Substation for generator interconnection to Hollow Branch Creek Solar (24INR0422). Loop into existing Ckt.74 Singleton to Jewett (ONCOR) to create new Ckt.74 Singleton to Skains to Jewett.
ERCOT project 89939A
CNP
Tier 4
Planned
Future tab
345 Oct 2027 Skains to Singleton/Jewett
Grimes / Leon County
Skains, Singleton, Jewett
Rebuild Pin Oak Switch - Jewett Switch 345 kV Double Circuit Line
ERCOT project 99620 · utility no. R1704 · RPG 25RPG004
ONCOR
Tier 1
Planned
Future tab
345 Dec 2028 Pin Oak Switch to Jewett Switch
Freestone / Leon County
Pin Oak Switch, Jewett Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026110000Status as reportedPlanned → Conceptual
October 1, 2026110381First listedon the Future tab
October 1, 2026111258AFirst listedon the Future tab
October 1, 2026111258BFirst listedon the Future tab
July 13, 2026110000First listedon the Future tab
June 1, 202699620First listedon the Future tab
February 1, 202589939AFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.