Pin Oak
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Freestone County. First named in the release with data as of June 1, 2021.
Also printed as: Pin Oak 345 kV Switch · Pin Oak Switch
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Freestone, TX: ERCOT queue, 24 active of 24. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Navarro Switch - Pin Oak Switch 345 kV DCKT Line Upgrade ERCOT project 105751 · utility no. R6428 · RPG 25RPG038 · RTP 2024-NC42 |
ONCOR Tier 1 |
Planned Future tab |
345 | May 2032 | Navarro to Pin Oak Navarro / Freestone County |
Navarro, Pin Oak |
| Rebuild Pin Oak Switch - Jewett Switch 345 kV Double Circuit Line ERCOT project 99620 · utility no. R1704 · RPG 25RPG004 |
ONCOR Tier 1 |
Planned Future tab |
345 | Dec 2028 | Pin Oak Switch to Jewett Switch Freestone / Leon County |
Pin Oak Switch, Jewett Switch |
| Establish Pin Oak 345 kV Switch ERCOT project 99622 · utility no. R6331 · RPG 25RPG004 |
ONCOR Tier 1 |
Planned Future tab |
345 | Dec 2027 | Pin Oak 345 kV Switch to Pin Oak 345 kV Switch Freestone County |
Pin Oak 345 kV Switch |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| June 1, 2026 | 105751 | First listed | on the Future tab |
| June 1, 2026 | 99620 | First listed | on the Future tab |
| June 1, 2026 | 99622 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.