Mulberry Creek

Named in 7 listed projects in ERCOT’s transmission project tracking workbook, in Jones County. First named in the release with data as of February 1, 2017.

Jonescounty as printed
138, 345kV
AEP TNC, ONCORutility
7projects listed

Expansion at an existing substation: named load connected. The quoted wording describes a named load being connected at this substation. “Interconnect the Lancium load to the Mulberry Creek 345 kV station” — project 77122, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Jones, TX: ERCOT queue, 18 active of 21. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Mulberry Creek: Rebuild 345 kV station
Rebuild Mulberry Creek 345 kV station and replace both autotransformers
ERCOT project 48816 · utility no. 2776 · RPG 21RPG021
AEP TNC
Tier 4
Under Construction
Completed tab
345 Jun 2025
actual 2025-06
Mulberry Creek
Jones County
Mulberry Creek
Rebuild and reconfigure the existing Mulberry Creek 345 kV Switch
ERCOT project 66569 · utility no. R9022 · RPG 21RPG021
ONCOR
Tier 3
Planned
Completed tab
345 May 2025
actual 2025-05
Mulberry Creek to Mulberry Creek
Jones County
Mulberry Creek
Mulberry Creek: Rebuild 138 kV Station
Rebuild Mulberry Creek 138 kV station
ERCOT project 73032 · RPG 25RPG034
AEP TNC
Tier 4
Planned
Future tab
138 Nov 2027 Mulberry Creek
Jones County
Mulberry Creek
Mulberry Creek: Construct New 345 kV Terminal
Interconnect the Lancium load to the Mulberry Creek 345 kV station
ERCOT project 77122
AEP TNC
Tier 4
Planned
Completed tab
345 Nov 2025
actual 2025-12
Mulberry Creek
Jones County
Mulberry Creek
Elm Creek to Mulberry Creek: Rebuild 138 kV Line
Rebuild the Elm Creek to Mulberry Creek 138 kV line
ERCOT project 90063 · utility no. TP2023600
AEP TNC
Tier 4
Planned
Future tab
138 May 2027 Elm Creek to Mulberry Creek
Taylor / Jones County
Elm Creek, Mulberry Creek
Abilene Northwest to Mulberry Creek: Rebuild 138 kV Line
Rebuild the Abilene Northwest to Mulberry Creek 138 kV line
ERCOT project 90065 · utility no. TP2023881
AEP TNC
Tier 4
Planned
Future tab
138 Jan 2027 Abilene Northwest to Mulberry Creek
Taylor / Jones County
Abilene Northwest, Mulberry Creek
Bluff Creek to Mulberry Creek: Rebuild 345 kV Line as a Double Circuit
Rebuild existing 345 kV line from Bluff Creek to Mulberry Creek as a double circuit line
ERCOT project 98599 · RPG H.B. 5066
AEP TNC
Tier 1
Planned
Future tab
345 Dec 2028 Bluff Creek to Mulberry Creek
Taylor / Jones County
Bluff Creek, Mulberry Creek

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202673032Projected in-service dateFeb 2027 → Nov 2027
October 1, 202690065Moved between tabsCurrent-year planned → Future
October 1, 202690065Projected in-service dateNov 2026 → Jan 2027
June 1, 202673032Projected in-service dateApr 2027 → Feb 2027
June 1, 202698599Projected in-service dateNov 2030 → Dec 2028
February 1, 202648816Moved between tabsCurrent-year planned → Completed
February 1, 202677122Moved between tabsCurrent-year planned → Completed
February 1, 202690065Moved between tabsFuture → Current-year planned
February 1, 202690065Projected in-service dateMay 2027 → Nov 2026
October 1, 202548816Projected in-service dateMay 2025 → Jun 2025
October 1, 202566569Moved between tabsCurrent-year planned → Completed
October 1, 202598599First listedon the Future tab
June 1, 202548816Moved between tabsFuture → Current-year planned
June 1, 202566569Moved between tabsFuture → Current-year planned
June 1, 202577122Moved between tabsFuture → Current-year planned
June 1, 202577122Projected in-service dateSep 2025 → Nov 2025
February 1, 202577122Projected in-service dateApr 2026 → Sep 2025
February 1, 202590063First listedon the Future tab
February 1, 202590065First listedon the Future tab
October 1, 202473032Projected in-service dateApr 2026 → Apr 2027
June 1, 202448816Status as reportedPlanned → Under Construction
June 1, 202473032Projected in-service dateNov 2025 → Apr 2026
June 1, 202477122First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.