Bluff Creek

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Taylor County. First named in the release with data as of May 12, 2023.

Taylorcounty as printed
138, 345kV
AEP TNCutility
3projects listed

A HIFLD substation record has the same name and county: BLUFF CREEK (TAYLOR County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Taylor, TX: ERCOT queue, 13 active of 15. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Bluff Creek: Upgrade Relaying and Communication
Upgrade the relaying and communication at the Bluff Creek 138 kV station to support the Buffalo Gap Wind Repower
ERCOT project 103299 · utility no. TP2025822
AEP TNC
Tier 4
Planned
Future tab
138 Apr 2027 Bluff Creek
Taylor County
Bluff Creek
Bluff Creek: 138 kV Station Work
Replace fourteen (14) 138 kV Breakers and one (1) Circuit Switcher
ERCOT project 72942
AEP TNC
Tier 4
In-Service
Completed tab
138 Jun 2026
actual 2026-04
Bluff Creek
Taylor County
Bluff Creek
Bluff Creek to Mulberry Creek: Rebuild 345 kV Line as a Double Circuit
Rebuild existing 345 kV line from Bluff Creek to Mulberry Creek as a double circuit line
ERCOT project 98599 · RPG H.B. 5066
AEP TNC
Tier 1
Planned
Future tab
345 Dec 2028 Bluff Creek to Mulberry Creek
Taylor / Jones County
Bluff Creek, Mulberry Creek

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202672942Moved between tabsCurrent-year planned → Completed
October 1, 202672942Status as reportedPlanned → In-Service
July 13, 202672942Projected in-service dateMar 2026 → Jun 2026
June 1, 2026103299First listedon the Future tab
June 1, 202698599Projected in-service dateNov 2030 → Dec 2028
February 1, 202672942Moved between tabsFuture → Current-year planned
February 1, 202672942Projected in-service dateFeb 2026 → Mar 2026
October 1, 202598599First listedon the Future tab
February 1, 202572942Projected in-service dateJul 2025 → Feb 2026
June 1, 202472942Projected in-service dateMay 2025 → Jul 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.