Abilene Northwest
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Taylor County. First named in the release with data as of February 1, 2015.
Taylorcounty as printed
138kV
AEP TNCutility
2projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Taylor, TX: ERCOT queue, 13 active of 15. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Abilene Northwest to Mulberry Creek: Rebuild 138 kV Line Rebuild the Abilene Northwest to Mulberry Creek 138 kV line ERCOT project 90065 · utility no. TP2023881 |
AEP TNC Tier 4 |
Planned Future tab |
138 | Jan 2027 | Abilene Northwest to Mulberry Creek Taylor / Jones County |
Abilene Northwest, Mulberry Creek |
| Abilene Northwest to Oak Creek: Reterminate 138 kV Line Into Nicole Reterminate the Abilene Northwest to Oak Creek 138 kV line from Oak Creek into the existing Nicole 138 kV station ERCOT project 98626 · RPG H.B. 5066 |
AEP TNC Tier 1 |
Planned Future tab |
138 | Nov 2029 | Abilene Northwest to Nicole Taylor / Coke County |
Abilene Northwest, Nicole |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 90065 | Moved between tabs | Current-year planned → Future |
| October 1, 2026 | 90065 | Projected in-service date | Nov 2026 → Jan 2027 |
| February 1, 2026 | 90065 | Moved between tabs | Future → Current-year planned |
| February 1, 2026 | 90065 | Projected in-service date | May 2027 → Nov 2026 |
| February 1, 2026 | 98626 | Projected in-service date | Dec 2030 → Nov 2029 |
| October 1, 2025 | 98626 | First listed | on the Future tab |
| February 1, 2025 | 90065 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.