Substation Scout

San Felipe

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Harris County. First named in the release with data as of June 1, 2015.

Harriscounty as printed
138kV
CNPutility
2projects listed

A HIFLD substation record has the same name and county: SAN FELIPE (HARRIS County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Harris, TX: ERCOT queue, 30 active of 35 · MISO queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Heights 138kV Loop Conversion
Convert Heights substation to 138kV service. Retire/repurpose portions of 69kV Ckts. 34A/34B for the new Heights 138kV loop. Reconfigure Ckt.09D to create new Ckt.09D Eureka TR2/TR3 tap to HE-DN_TR1 tap to Heights 138kV to White Oak. Reconductor any existing 1-795AAC limiting conductor to 2-959ACSS. Remove existing Heights 7.2 MVAR cap bank from Heights TR1.
ERCOT project 73578D
CNP
Tier 4
Planned
Current-year planned tab
138 Oct 2026 Heights to San Felipe/White Oak
Harris County
Heights, San Felipe, White Oak
Heights 138kV Loop Conversion
Convert Eureka to double-tap service. Tap Ckt.09D to create new Ckt.09D San Felipe to Eureka TR2/TR3 tap to White Oak. Reconductor Ckt.09D Eureka TR2/TR3 tap to White Oak to increase thermal limits. Upgrade San Felipe line relaying Ckt.09D San Felipe to White Oak.
ERCOT project 73578K
CNP
Tier 4
In-Service
Completed tab
138 May 2025
actual 2025-05
San Felipe to White Oak
Harris County
San Felipe, White Oak

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202673578DMoved between tabsFuture → Current-year planned
February 1, 202673578DProjected in-service dateMay 2026 → Oct 2026
June 1, 202573578KMoved between tabsFuture → Completed
June 1, 202573578KStatus as reportedPlanned → In-Service
February 1, 202573578KFirst listedon the Future tab
October 1, 202473578DProjected in-service dateDec 2025 → May 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.