Substation Scout

Mont Belvieu

Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Chambers County. First named in the release with data as of June 1, 2020.

Chamberscounty as printed
138kV
CNPutility
4projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Chambers, TX: ERCOT queue, 2 active of 3 · MISO queue, 1 active of 3. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
BRINE Substation Upgrades
Upgrade substation equipment at BRINE on Ckt.86H DALTON to BRINE to Mont Belvieu.
ERCOT project 76369
CNP
Tier 4
Planned
Future tab
138 May 2027 BRINE to DALTON/Mont Belvieu
Chambers County
BRINE, DALTON, Mont Belvieu
Jordan / Mont Belvieu Area Improvement Project
Install 120 MVAr cap bank at Mont Belvieu Ckt.84E to WARVUE.
ERCOT project 90255A · RPG 24RPG026
CNP
Tier 3
Planned
Future tab
138 May 2027 Mont Belvieu to WARVUE
Chambers County
Mont Belvieu, WARVUE
Jordan / Mont Belvieu Area Improvement Project
Upgrade Ckt.86H BRINE to Mont Belvieu to increase thermal limits.
ERCOT project 90255D · RPG 24RPG026
CNP
Tier 3
Planned
Future tab
138 Apr 2028 BRINE to Mont Belvieu
Chambers County
BRINE, Mont Belvieu
Jordan / Mont Belvieu Area Improvement Project
Apply 110% Emergency rating for the EAGLE customer substation 2000A equipment to increase thermal limits on Ckts 52B / 52C. Upgrade existing 515 / 515 MVA Mont Belvieu relay system limits on Ckt.52C line position.
ERCOT project 90255E · RPG 24RPG026
CNP
Tier 3
Planned
Future tab
138 May 2027 EAGLE to WINFRE/Mont Belvieu
Chambers County
EAGLE, WINFRE, Mont Belvieu

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202690255DProjected in-service dateMar 2028 → Apr 2028
July 13, 202690255DProjected in-service dateJun 2027 → Mar 2028
July 13, 202690255DProjected in-service dateMay 2027 → Jun 2027
October 1, 202576369Moved between tabsCompleted → Future
October 1, 202576369Projected in-service dateFeb 2025 → May 2027
June 1, 202576369Projected in-service dateJan 2025 → Feb 2025
February 1, 202576369Projected in-service dateSep 2024 → Jan 2025
February 1, 202590255AFirst listedon the Future tab
February 1, 202590255DFirst listedon the Future tab
February 1, 202590255EFirst listedon the Future tab
October 1, 202476369Moved between tabsFuture → Completed
June 1, 202476369Moved between tabsCompleted → Future
June 1, 202476369Projected in-service dateJan 2024 → Sep 2024

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.