Cedar Bayou
Named in 9 listed projects in ERCOT’s transmission project tracking workbook, in Chambers County. First named in the release with data as of February 1, 2015.
No HIFLD substation record has this name in this county (a record of the same name exists in another county).
Generation interconnection requests filed in Chambers, TX: ERCOT queue, 2 active of 3 · MISO queue, 1 active of 3. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Cedar Bayou 5 Generator Interconnection (23INR0029) Connect new generation facility to Cedar Bayou 345kV substation with 721 MW combined cycle natural gas-fired units. ERCOT project 90173A |
CNP Tier 4 |
Planned Future tab |
345 | Jun 2027 | Cedar Bayou Chambers County |
Cedar Bayou |
| Cedar Bayou 5 Generator Interconnection (23INR0029) Upgrade Ckt.97E Cedar Bayou to Chambers to increase thermal limits. ERCOT project 90173B |
CNP Tier 4 |
Planned Future tab |
345 | Jun 2027 | Cedar Bayou to Chambers Chambers County |
Cedar Bayou, Chambers |
| Jordan / Mont Belvieu Area Improvement Project Upgrade Ckt.84D Cedar Bayou to CD/HOPSON to increase thermal limits. ERCOT project 90255B · RPG 24RPG026 |
CNP Tier 3 |
Planned Future tab |
138 | May 2027 | Cedar Bayou to Cedar Bayou Distribution Chambers County |
Cedar Bayou, Cedar Bayou Distribution |
| Jordan / Mont Belvieu Area Improvement Project Upgrade Ckt.86A Cedar Bayou to CHEVRON to increase thermal limits. ERCOT project 90255C · RPG 24RPG026 |
CNP Tier 3 |
Planned Future tab |
138 | May 2027 | Cedar Bayou to CHEVRON Chambers / Harris County |
Cedar Bayou, CHEVRON |
| Jordan / Mont Belvieu Area Improvement Project Install new CEHE-owned Sjolander substation. Reconfigure existing Ckt.84D Cedar Bayou to CD/HOPSON and loop into Sjolander substation to create new Ckt.84 Cedar Bayou to Cedar Bayou tap to Sjolander to HOPSON. ERCOT project 90255F · RPG 24RPG026 |
CNP Tier 3 |
Planned Future tab |
138 | May 2028 | Sjolander to Cedar Bayou /HOPSON Chambers County |
Sjolander, Cedar Bayou, HOPSON |
| Jordan / Mont Belvieu Area Improvement Project Install new CEHE-owned Sjolander substation. Reconfigure existing Ckt.86A Cedar Bayou to CHEVRON and loop into Sjolander substation to create new Ckt.86 Cedar Bayou to Sjolander to Kilgore to Langston. ERCOT project 90255G · RPG 24RPG026 |
CNP Tier 3 |
Planned Future tab |
138 | May 2028 | Cedar Bayou to Sjolander Chambers County |
Cedar Bayou, Sjolander |
| Cedar Bayou RPG - Substation Upgrades (25RPG014) Replace existing 600 MVA 345/138kV Cedar Bayou Auto A1 with new 800 MVA autotransformer. Install 2.5-Ohm reactor in-series with new CBY-A1 on the 138kV side of the autotransformer. ERCOT project 99274A · RPG 25RPG014 |
CNP Tier 3 |
Planned Future tab |
345 | May 2028 | Cedar Bayou Chambers County |
Cedar Bayou |
| Cedar Bayou RPG - Substation Upgrades (25RPG014) Replace existing Cedar Bayou parallel 345/138kV autotransformers 2A/2B with new 800 MVA autotransformer as CBY-A2. Remove existing 10-Ohm reactor from the 138kV side of the 2A/2B parallel autotransformers. Replace with 2.5-Ohm reactor in-series with new CBY-A2 on the 138kV side of the autotransformer. ERCOT project 99274B · RPG 25RPG014 |
CNP Tier 3 |
Planned Future tab |
345 | May 2028 | Cedar Bayou Chambers County |
Cedar Bayou |
| Cedar Bayou RPG - Substation Upgrades (25RPG014) Install 2.5-Ohm reactor in-series with existing Cedar Bayou A3 on the 138kV side of the autotransformer. ERCOT project 99274C · RPG 25RPG014 |
CNP Tier 3 |
Planned Future tab |
138 | May 2028 | Cedar Bayou Chambers County |
Cedar Bayou |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| June 1, 2026 | 90255F | Projected in-service date | May 2027 → May 2028 |
| June 1, 2026 | 90255G | Projected in-service date | May 2027 → May 2028 |
| October 1, 2025 | 99274A | First listed | on the Future tab |
| October 1, 2025 | 99274B | First listed | on the Future tab |
| October 1, 2025 | 99274C | First listed | on the Future tab |
| June 1, 2025 | 90255F | First listed | on the Future tab |
| June 1, 2025 | 90255G | First listed | on the Future tab |
| February 1, 2025 | 90173A | First listed | on the Future tab |
| February 1, 2025 | 90173B | First listed | on the Future tab |
| February 1, 2025 | 90255B | First listed | on the Future tab |
| February 1, 2025 | 90255C | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.