Substation Scout

Cedar Bayou

Named in 9 listed projects in ERCOT’s transmission project tracking workbook, in Chambers County. First named in the release with data as of February 1, 2015.

Chamberscounty as printed
138, 345kV
CNPutility
9projects listed

No HIFLD substation record has this name in this county (a record of the same name exists in another county).

Generation interconnection requests filed in Chambers, TX: ERCOT queue, 2 active of 3 · MISO queue, 1 active of 3. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Cedar Bayou 5 Generator Interconnection (23INR0029)
Connect new generation facility to Cedar Bayou 345kV substation with 721 MW combined cycle natural gas-fired units.
ERCOT project 90173A
CNP
Tier 4
Planned
Future tab
345 Jun 2027 Cedar Bayou
Chambers County
Cedar Bayou
Cedar Bayou 5 Generator Interconnection (23INR0029)
Upgrade Ckt.97E Cedar Bayou to Chambers to increase thermal limits.
ERCOT project 90173B
CNP
Tier 4
Planned
Future tab
345 Jun 2027 Cedar Bayou to Chambers
Chambers County
Cedar Bayou, Chambers
Jordan / Mont Belvieu Area Improvement Project
Upgrade Ckt.84D Cedar Bayou to CD/HOPSON to increase thermal limits.
ERCOT project 90255B · RPG 24RPG026
CNP
Tier 3
Planned
Future tab
138 May 2027 Cedar Bayou to Cedar Bayou Distribution
Chambers County
Cedar Bayou, Cedar Bayou Distribution
Jordan / Mont Belvieu Area Improvement Project
Upgrade Ckt.86A Cedar Bayou to CHEVRON to increase thermal limits.
ERCOT project 90255C · RPG 24RPG026
CNP
Tier 3
Planned
Future tab
138 May 2027 Cedar Bayou to CHEVRON
Chambers / Harris County
Cedar Bayou, CHEVRON
Jordan / Mont Belvieu Area Improvement Project
Install new CEHE-owned Sjolander substation. Reconfigure existing Ckt.84D Cedar Bayou to CD/HOPSON and loop into Sjolander substation to create new Ckt.84 Cedar Bayou to Cedar Bayou tap to Sjolander to HOPSON.
ERCOT project 90255F · RPG 24RPG026
CNP
Tier 3
Planned
Future tab
138 May 2028 Sjolander to Cedar Bayou /HOPSON
Chambers County
Sjolander, Cedar Bayou, HOPSON
Jordan / Mont Belvieu Area Improvement Project
Install new CEHE-owned Sjolander substation. Reconfigure existing Ckt.86A Cedar Bayou to CHEVRON and loop into Sjolander substation to create new Ckt.86 Cedar Bayou to Sjolander to Kilgore to Langston.
ERCOT project 90255G · RPG 24RPG026
CNP
Tier 3
Planned
Future tab
138 May 2028 Cedar Bayou to Sjolander
Chambers County
Cedar Bayou, Sjolander
Cedar Bayou RPG - Substation Upgrades (25RPG014)
Replace existing 600 MVA 345/138kV Cedar Bayou Auto A1 with new 800 MVA autotransformer. Install 2.5-Ohm reactor in-series with new CBY-A1 on the 138kV side of the autotransformer.
ERCOT project 99274A · RPG 25RPG014
CNP
Tier 3
Planned
Future tab
345 May 2028 Cedar Bayou
Chambers County
Cedar Bayou
Cedar Bayou RPG - Substation Upgrades (25RPG014)
Replace existing Cedar Bayou parallel 345/138kV autotransformers 2A/2B with new 800 MVA autotransformer as CBY-A2. Remove existing 10-Ohm reactor from the 138kV side of the 2A/2B parallel autotransformers. Replace with 2.5-Ohm reactor in-series with new CBY-A2 on the 138kV side of the autotransformer.
ERCOT project 99274B · RPG 25RPG014
CNP
Tier 3
Planned
Future tab
345 May 2028 Cedar Bayou
Chambers County
Cedar Bayou
Cedar Bayou RPG - Substation Upgrades (25RPG014)
Install 2.5-Ohm reactor in-series with existing Cedar Bayou A3 on the 138kV side of the autotransformer.
ERCOT project 99274C · RPG 25RPG014
CNP
Tier 3
Planned
Future tab
138 May 2028 Cedar Bayou
Chambers County
Cedar Bayou

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202690255FProjected in-service dateMay 2027 → May 2028
June 1, 202690255GProjected in-service dateMay 2027 → May 2028
October 1, 202599274AFirst listedon the Future tab
October 1, 202599274BFirst listedon the Future tab
October 1, 202599274CFirst listedon the Future tab
June 1, 202590255FFirst listedon the Future tab
June 1, 202590255GFirst listedon the Future tab
February 1, 202590173AFirst listedon the Future tab
February 1, 202590173BFirst listedon the Future tab
February 1, 202590255BFirst listedon the Future tab
February 1, 202590255CFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first