Rio Hondo

Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in Cameron County. First named in the release with data as of February 1, 2015.

Cameroncounty as printed
138, 345kV
AEP TCC, STECutility
4projects listed

A HIFLD substation record has the same name and county: RIO HONDO (CAMERON County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Cameron, TX: ERCOT queue, 30 active of 32. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Rio Hondo: 138 kV Breaker Replacement
Replace 138 kV breakers at the Rio Hondo 138 kV station
ERCOT project 103414 · utility no. TP2025950
AEP TCC
Tier 4
Planned
Future tab
138 Oct 2028 Rio Hondo
Cameron County
Rio Hondo
Rio Hondo to Bonilla: Rebuild/Reconductor 345 kV Line
Rebuild/Reconductor Rio Hondo to Bonilla 345 kV line
ERCOT project 110437
AEP TCC
Tier 3
Planned
Future tab
345 May 2028 Rio Hondo to Bonilla
Cameron County
Rio Hondo, Bonilla
Rebuild Rio Hondo to East Rio Hondo
Rebuild the 138 kV line from Rio Hondo to East Rio Hondo.
ERCOT project 6687
STEC
Tier 4
Conceptual
Future tab
138 Jun 2029 Rio Hondo to East Rio Hondo
Cameron County
Rio Hondo, East Rio Hondo
Upgrade RIOHONDO to BURNS line
Upgrade RIOHONDO to BURNS line to be 478MVA capable
ERCOT project 71930
STEC
Tier 4
Under Construction
Completed tab
138 May 2025
actual 2025-07
Rio Hondo to Burns
Cameron County
Rio Hondo, Burns

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026103414Projected in-service dateMar 2028 → Oct 2028
October 1, 2026110437Status as reportedConceptual → Planned
October 1, 2026110437Projected in-service dateJun 2028 → May 2028
July 13, 2026110437First listedon the Future tab
June 1, 2026103414First listedon the Future tab
October 1, 20256687Status as reportedPlanned → Conceptual
October 1, 202571930Moved between tabsCurrent-year planned → Completed
June 1, 202571930Moved between tabsFuture → Current-year planned
February 1, 202571930Status as reportedPlanned → Under Construction

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.