Bonilla

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Cameron County. First named in the release with data as of February 1, 2016.

Cameroncounty as printed
345kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Cameron, TX: ERCOT queue, 30 active of 32. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Rio Hondo to Bonilla: Rebuild/Reconductor 345 kV Line
Rebuild/Reconductor Rio Hondo to Bonilla 345 kV line
ERCOT project 110437
AEP TCC
Tier 3
Planned
Future tab
345 May 2028 Rio Hondo to Bonilla
Cameron County
Rio Hondo, Bonilla

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026110437Status as reportedConceptual → Planned
October 1, 2026110437Projected in-service dateJun 2028 → May 2028
July 13, 2026110437First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.