San Miguel

Named in 5 listed projects in ERCOT’s transmission project tracking workbook, in Atascosa County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2015.

Atascosacounty as printed
138, 345kV
BEPC, STECutility
5projects listed

A HIFLD substation record has the same name and county: SAN MIGUEL (ATASCOSA County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Atascosa, TX: ERCOT queue, 17 active of 17. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade Pawnee - San Miguel 138
(5727) PAWNEE SWITCHING STATION to (5902) SAN MIGUEL GEN 138 kV Ckt 1 Rebuild [276 MVA Minimum]
ERCOT project 110189
STEC
Tier 4
Conceptual
Future tab
138 Jan 2031 Pawnee to San Miguel
Karnes / Atascosa County
Pawnee, San Miguel
No title printed
ERCOT project 110254 · RPG 26RPG026 · RTP 2025-SC20
BEPC
Tier 1
Planned
Future tab
345 Apr 2031 San Miguel to Marion
Atascosa / Comal County
San Miguel, Marion
STEC Amphion Load Project Phase 1
-Hairpin San Miguel to Fowlerton ckt 2 into STEC Amphion load serving station -Loop in and out San Miguel to Cruce into STEC Amphion load station
ERCOT project 110455
STEC
Tier 2
Conceptual
Future tab
345 Jan 2030 San Miguel to Fowlerton, Cruce
Atascosa / McMullen County
San Miguel, Fowlerton, Cruce
STEC Amphion Load Project Phase3
-RTP project 2024-CS1: Upgrade Cachena to Old Hickory ckt 2 to 1072MVA -RTP Project 2025-SC20: Upgrade Cachena to Elm Creek ckt 2 to 1965 MVA -RTP Project 2024-SC26: Upgrade Elm Creek to Shaula ckt 1 to 1746 MVA -Upgrade Pawnee to San Miguel 345 to 1810 MVA
ERCOT project 110459
STEC
Tier 2
Conceptual
Future tab
345 Jul 2031 Pawnee to San Miguel
Karnes / Atascosa County
Pawnee, San Miguel
San Miguel to Cruce 345 kV lines
New San Miguel to Cruce 345 kV double circuit lines
ERCOT project 67329 · RPG 21RPG017
STEC
Tier 1
Planned
Future tab
345 Jan 2027 San Miguel to Cruce
Atascosa / Duval County
San Miguel, Cruce

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
San Miguel to Sigmor 138 kV line upgrade
Upgrade San Miguel to Sigmor 138 kV line as recommended in 2013 RTP. Will investigate re-conductoring on existing structures with ACCC and other high temperature conductors.
ERCOT project 3822 · RTP 2013-R102
STEC
Tier 3
Conceptual
Cancelled tab
138 Jun 2031 San Miguel to Sigmor
Atascosa / Live Oak County
San Miguel, Sigmor

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202667329Moved between tabsCurrent-year planned → Future
October 1, 202667329Projected in-service dateDec 2026 → Jan 2027
July 13, 2026110189First listedon the Future tab
July 13, 2026110254First listedon the Future tab
July 13, 2026110455First listedon the Future tab
July 13, 2026110459First listedon the Future tab
February 1, 202667329Moved between tabsFuture → Current-year planned

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.