Sigmor
Named in 0 listed projects in ERCOT’s transmission project tracking workbook, in Live Oak County, plus 1 on its Cancelled tab. First named in the release with data as of February 1, 2015.
Live Oakcounty as printed
138kV
STECutility
0projects listed
Projects cancelled. Every project naming Sigmor is on the Cancelled tab of ERCOT's workbook.
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Live Oak, TX: ERCOT queue, 5 active of 8. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
No projects.
On the Cancelled tab
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| San Miguel to Sigmor 138 kV line upgrade Upgrade San Miguel to Sigmor 138 kV line as recommended in 2013 RTP. Will investigate re-conductoring on existing structures with ACCC and other high temperature conductors. ERCOT project 3822 · RTP 2013-R102 |
STEC Tier 3 |
Conceptual Cancelled tab |
138 | Jun 2031 | San Miguel to Sigmor Atascosa / Live Oak County |
San Miguel, Sigmor |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.