Herty Tap

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Angelina County. First named in the release with data as of October 1, 2025.

Angelinacounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Angelina, TX: ERCOT queue, 5 active of 5. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade Redland Switch - Herty Tap 138 kV Line Section
ERCOT project 99624 · utility no. R6291
ONCOR
Tier 4
Planned
Future tab
138 May 2027 Redland 138 kV Switch to Herty Tap
Angelina County
Redland 138 kV Switch, Herty Tap

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202699624Projected in-service dateDec 2027 → May 2027
June 1, 202699624Projected in-service dateMay 2027 → Dec 2027
February 1, 202699624Projected in-service dateMay 2028 → May 2027
October 1, 202599624First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.