Substation Scout

Taylor County

Named in 1 PJM planning document for 2 projects, on Not reported.

Existingdescribed as
EKPCzone
161/69 kV, 69 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Metts Dr
EKPC-2023-014 · s3172.0
Engineering $2.95M 7/1/2025 Not printed 2026-09-08*
SRRTEP Western
Green County/Coburg Junction Area
EKPC-2023-018 · s3175.0
Conceptual $22.1M 12/31/2026 Not printed 2026-09-08*
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named LEBANON; METTS DRIVE; SOUTH MARION COUNTY INDUSTRIAL → GREEN COUNTY; KU LEBANON SOUTH; LEBANON; MARION COUNTY; METTS DRIVE; SOUTH MARION COUNTY INDUSTRIAL; TAYLOR COUNTY 2024-10-08 Not reported
Substations named CAMPBELLSVILLE; COBURG JUNCTION → BASS; CAMPBELLSVILLE; COBURG; COBURG JUNCTION; EAST CAMPBELLSVILLE; GREEN COUNTY; HEARTLAND; SUMMER SHADE; TAYLOR COUNTY 2024-10-08 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
EKPC local plan submission of the supplemental projects for 2024 RTEP p. 19
Metts Dr No role wording
69 kV
2026-09-08* SRRTEP Western
EKPC local plan submission of the supplemental projects for 2024 RTEP p. 24
Green County/Coburg Junction Area “upgrade the LG&E/KU Taylor County substation”
161/69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this