Keeney

Named in 4 PJM planning documents for 1 project, from September 18, 2025 to October 6, 2026.

Existingdescribed as
DPLzone
138 kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
DPL-2025-002 Not printed $0.15 million 12/12/2025 Not printed 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 12/24/2025 → 12/12/2025 2025-10-16 2026-10-06
Status under-construction (Construction) → unknown (Complete) 2025-10-16 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - DPL Local Plan Submission of Supplemental Projects for 2026 p. 5
DPL-2025-002 “Upgrade bus conductor at Keeney 138 kV from 954 ACSR to 2-954 ACSR.”
138 kV
2026-10-01* SRRTEP Mid-Atlantic
DPL local plan submission for 2026 RTEP p. 5
DPL-2025-002 “Upgrade bus conductor at Keeney 138 kV”
138 kV
2025-10-16 SRRTEP Mid-Atlantic
Item 04 - DPL Supplemental Projects p. 4
DPL-2025-002 “Upgrade bus conductor at Keeney 138 kV from 954 ACSR to 2- 954 ACSR”
138 kV
2025-09-18 SRRTEP Mid-Atlantic
Item 04 - DPL Supplemental Projects p. 3
DPL-2025-002 No role wording
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this