Pantego

Named in 1 PJM planning document for 1 project, on December 12, 2024.

Not stateddescribed as
DOMzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Line #1031 Pantego to Terra 115kV
b3922.1
Not printed $29.4M 6/1/2029 Not printed 2024-12-12
SRRTEP Southern

Every mention

DateDocumentProjectWhat the document says about it
2024-12-12 SRRTEP Southern
Item 01 - SRRTEP South - Reliability Analysis Update p. 9
Line #1031 Pantego to Terra 115kV No role wording