Kraken

Named in 11 PJM planning documents for 9 projects, from April 1, 2025 to October 6, 2026.

Newdescribed as
DOMzone
500kVkV as printed
13mentions

Described as new: “Construct one (1) new 500kV line terminal position at the proposed Kraken substation.” — source, page 36

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dominion Transmission Zone: Baseline New 500kV Line North Anna - Thornburg - Bristers
b4000.344 & b4000.345
Not printed $661.63M 9/16/2030 Not printed 2026-05-08
TEAC
Thornburg 500/230kV Substation (Line #568 Ladysmith – Possum Point Cut-In)
b4000.351 & b4000.352
Not printed $7.2M 9/16/2030 Not printed 2026-10-06
TEAC
Dominion Transmission Zone: Baseline New 765/500/230kV Yeat Substation
B4000.355 – B4000.359
Not printed $1,109.89M 6/1/2029 Not printed 2026-05-08
TEAC
Regional Solution: 2025-W1-275 Portfolio
b4053.1
Not printed $4832.45 6/1/2032 Not printed 2026-01-06
TEAC
Dominion Transmission Zone: Supplemental Do No Harm Analysis
DOM-2023-0016 · s3731
Engineering $27 M 05/31/2025 248.0 MW 2026-10-06
TEAC
Matta 230kV Delivery - DEV
DOM-2023-0023
Engineering $25.5 M 11/15/2026 300 MW 2025-09-09
TEAC
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency
DOM-2024-0051
Conceptual Transmission: $108M; Substation: $15M 12/31/2030 Not printed 2025-06-05
TEAC
Emy 230kV Delivery - REC
DOM-2025-0051 · s4029
Conceptual $26M 05/01/2030 212 MW 2026-10-06
TEAC
Dominion Transmission Zone: Baseline Regional Solution: 2025-W1-275 Portfolio
2025-W1-275
Not printed Not printed 6/1/2032 Not printed 2025-12-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$704.25 M → $704.33 M 2025-01-07 2025-01-07
Cost estimate
prior value printed on the same page
$571.63M → $661.63M 2026-05-08 2026-05-08
Cost estimate $704.33 M → $661.63M 2025-01-07 2026-05-08
In-service date 6/1/2029 → 9/16/2030 2025-01-07 2026-05-08
Substations named ELMONT; KRAKEN; LADYSMITH; NORTH ANNA; POSSUM POINT; YEAT → AQUIA HARBOR; BRISTERS; KRAKEN; LADYSMITH; NORTH ANNA; STAFFORD; THORNBURG 2025-01-07 2026-05-08
Cost estimate
prior value printed on the same page
$1,055.3 M → $1,109.89M 2025-01-07 2025-01-07
Cost estimate
prior value printed on the same page
$1,109.89M → $978.76 M 2026-08-04 2026-08-04
Cost estimate $1,109.89M → $978.76 M 2026-05-08 2026-08-04
Substations named BRISTERS; ELK RUN; JOSHUA FALLS; MEADOWBROOK; VINT HILL; YEAT → BRISTERS; CULPEPER YEAT; CUNNINGHAM; ELK RUN; ELMONT; JOSHUA FALLS; KRAKEN; MEADOWBROOK; MIDLOTHIAN; MORRISVILLE; MOSBY; NOKESVILLE; NORTH ANNA; POSSUM PT; SPOTSYLVANIA; VINT HILL; VONTAY; WISHING STAR; YEAT 2025-01-07 2026-04-07
Substations named BRISTERS; CULPEPER YEAT; CUNNINGHAM; ELK RUN; ELMONT; JOSHUA FALLS; KRAKEN; MEADOWBROOK; MIDLOTHIAN; MORRISVILLE; MOSBY; NOKESVILLE; NORTH ANNA; POSSUM PT; SPOTSYLVANIA; VINT HILL; VONTAY; WISHING STAR; YEAT → ANDERSON BRANCH; BRISTERS; CULPEPER YEAT; ELK RUN; ELMONT; JOSHUA FALLS; KRAKEN; MEADOWBROOK; MORRISVILLE; MOSBY; NOKESVILLE; POSSUM PT; SPOTSYLVANIA; VINT HILL; VONTAY; WISHING STAR; YEAT 2026-04-07 2026-05-08
Substations named ANDERSON BRANCH; BRISTERS; CULPEPER YEAT; ELK RUN; ELMONT; JOSHUA FALLS; KRAKEN; MEADOWBROOK; MORRISVILLE; MOSBY; NOKESVILLE; POSSUM PT; SPOTSYLVANIA; VINT HILL; VONTAY; WISHING STAR; YEAT → BRISTERS; CLOVERDALE; ELK RUN; JOSHUA FALLS; MEADOWBROOK; VINT HILL; YEAT 2026-05-08 2026-08-04
Cost estimate $27.0 M → $450.0M 2025-04-01 2026-06-02
Cost estimate $450.0M → $27 M 2026-06-02 2026-10-06
In-service date 05/31/2025 → 07/01/2029 2025-04-01 2026-06-02
In-service date 07/01/2029 → 05/31/2025 2026-06-02 2026-10-06
Substations named ALLMAN; ELMONT; FOUR RIVERS; FREDERICKSBURG; KRAKEN; LADYSMITH; LADYSMITH CT; LEES HILL; N DOSWELL; NEW POST; PINEWOOD; RUTHER GLEN; ST JOHNS → ALLMAN; CHANCELLOR; ELMONT; FOUR RIVERS; FREDERICKSBURG; KRAKEN; LADYSMITH; LADYSMITH CT; LEES HILL; N DOSWELL; NEW POST; PINEWOOD; POSSUM POINT; RUTHER GLEN; ST JOHNS; THORNBURG 2025-04-01 2026-06-02
Substations named ALLMAN; CHANCELLOR; ELMONT; FOUR RIVERS; FREDERICKSBURG; KRAKEN; LADYSMITH; LADYSMITH CT; LEES HILL; N DOSWELL; NEW POST; PINEWOOD; POSSUM POINT; RUTHER GLEN; ST JOHNS; THORNBURG → ALLMAN; ELMONT; FOUR RIVERS; FREDERICKSBURG; KRAKEN; LADYSMITH; LADYSMITH CT; NEW POST; PINEWOOD; POSSUM POINT; RUTHER GLEN; ST JOHNS; THORNBURG 2026-06-02 2026-10-06
Substations named KRAKEN; LADYSMITH CT; MATTA → LADYSMITH CT; ORROCK MATTA; THORNBURG 2025-09-09 2026-10-06
Cost estimate
prior value printed on the same page
$108M → $165M 2026-06-02 2026-06-02
Cost estimate Transmission: $108M; Substation: $15M → $165M 2025-06-05 2026-06-02
Cost estimate $165M → $185M 2026-06-02 2026-10-06
Status conceptual (Conceptual) → engineering (Engineering) 2025-06-05 2026-06-02
Substations named EMY → EMY; KRAKEN; NEW POST; TRIBUTARY 2025-11-04 2026-02-03

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 51
Dominion Transmission Zone: Supplemental Do No Harm Analysis No role wording
2026-10-06 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2026 p. 75
Emy 230kV Delivery - REC No role wording
2026-10-06 TEAC
Item 16 - Reliability Analysis Update - Presentation p. 8
Thornburg 500/230kV Substation (Line #568 Ladysmith – Possum Point Cut-In) “into Kraken”
2026-06-02 TEAC
Item 11 - DOM Supplemental Projects p. 10
Dominion Transmission Zone: Supplemental Do No Harm Analysis “Expand Thornburg (fka Kraken) 500kV Switching Station”
500kV
2026-05-08 TEAC
Item 10 - Reliability Analysis Update p. 14
Dominion Transmission Zone: Baseline New 500kV Line North Anna - Thornburg - Bristers “formerly Kraken”
2026-05-08 TEAC
Item 10 - Reliability Analysis Update p. 19
Dominion Transmission Zone: Baseline New 765/500/230kV Yeat Substation “new substation called Kraken”
500kV
2026-04-07 TEAC
Item 11 - Reliability Analysis Update p. 15
Dominion Transmission Zone: Baseline New 765/500/230kV Yeat Substation “Build a 500kV line from a new substation called Kraken”
500kV
2026-02-03 TEAC
Item 12 - DOM Supplemental Projects p. 8
Emy 230kV Delivery - REC No role wording
2026-01-06 TEAC
Item 09 - Reliability Analysis Update p. 36
Regional Solution: 2025-W1-275 Portfolio “Construct one (1) new 500kV line terminal position at the proposed Kraken substation.”
500kV
2025-12-08 TEAC
Item 11 - Reliability Analysis Update p. 82
Dominion Transmission Zone: Baseline Regional Solution: 2025-W1-275 Portfolio “Construct one (1) new 500kV line terminal position at the proposed Kraken substation.”
500kV
2025-09-09 TEAC
Item 14 - DOM Supplemental Projects p. 6
Matta 230kV Delivery - DEV No role wording
2025-06-05 TEAC
Item 08 - DOM Supplemental Projects p. 12
Dominion Transmission Zone: Supplemental Operational Flexibility and Efficiency No role wording
2025-04-01 TEAC
Item 11 - DOM Supplemental Projects p. 16
Dominion Transmission Zone: Supplemental Do No Harm Analysis “Expand Kraken 500kV Switching Station”
500kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.