Harrisonburg

Named in 2 PJM planning documents for 2 projects, on October 8, 2024.

Existingdescribed as
DOMzone
—kV as printed
4mentions

Also printed as: Harrisonburg Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Harrisonburg TX#1 Upgrade - DEV
DOM-2023-0029 · s3527.1
Under construction $0.35 M 12/31/2024 Not printed 2024-10-08
TEAC
230 kV Line #260 – EOL Rebuild
DOM-2024-0014 · s3506.1
Conceptual $28.0 M 12/31/2027 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Southern
Dominion p. 177
230 kV Line #260 – EOL Rebuild “Line#260 from Harrisonburg to Grottoes”
2026-09-08* SRRTEP Southern
Dominion p. 185
Harrisonburg TX#1 Upgrade - DEV “upgrade TX #1 at Harrisonburg Substation”
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 177
230 kV Line #260 – EOL Rebuild No role wording
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 185
Harrisonburg TX#1 Upgrade - DEV “upgrade TX #1 at Harrisonburg Substation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.