Goose Creek Substation

Named in 3 PJM planning documents for 2 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
DOMzone
500-230 kV, 500kVkV as printed
3mentions

Also printed as: Goose Creek

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Baseline 502 Jct-Woodside-Aspen 500 kV & Doubs Corridor Projects (DOM Portion)
b3800.118, b3800.120 & b3800.375
Not printed $73.94M 9/30/2030 (b3800.120 & b3800.375), 6/1/2028 (b3800.118) Not printed 2026-10-06
TEAC
Do No Harm Analysis
DOM-2021-0016-DNH · s2609.2
In service $40.0 M 12/15/2023 Not printed 2024-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$51.19M → $73.94M 2026-10-06 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Item 16 - Reliability Analysis Update - Presentation p. 7
Baseline 502 Jct-Woodside-Aspen 500 kV & Doubs Corridor Projects (DOM Portion) “Terminate new NextEra 500 kV line from Woodside into Goose Creek substation”
500kV
2026-09-08* SRRTEP Southern
Dominion p. 9
Do No Harm Analysis “Extend the existing 500kV ring bus at Goose Creek Substation”
500-230 kV
2024-10-08 TEAC
Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 9
Do No Harm Analysis “Extend the existing 500kV ring bus at Goose Creek Substation”
500-230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.