Davis
Named in 4 PJM planning documents for 4 projects, from October 8, 2024 to April 14, 2026.
Existingdescribed as
DOMzone
230 kV, 230/69/13.2 kV, 69 kVkV as printed
5mentions
Also printed as: Davis Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Replace Davis TX#2 - DEV DOM-2022-0053 · s3059 |
Under construction | $4.5 M | 05/31/2024 | Not printed | 2024-10-08 TEAC |
| Dominion Transmission Zone: Supplemental
Equipment Material Condition, Performance and Risk DOM-2025-0088 |
Not printed | Not printed | Not printed | 120 MW | 2026-04-07 TEAC |
| Equipment Material Condition, Performance and Risk DOM-2025-0089 |
Not printed | Not printed | Not printed | 30 MW | 2026-04-14 SRRTEP Southern |
| Equipment Material Condition, Performance and Risk DOM-2025-0095 |
Not printed | Not printed | Not printed | Not printed | 2026-04-14 SRRTEP Southern |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Southern Dominion p. 94 |
Replace Davis TX#2 - DEV | “Replace Davis TX#2” 230/69/13.2 kV |
| 2026-04-14 | SRRTEP Southern Item 01 - DOM Supplemental Projects p. 3 |
Equipment Material Condition, Performance and Risk | No role wording |
| 2026-04-14 | SRRTEP Southern Item 01 - DOM Supplemental Projects p. 4 |
Equipment Material Condition, Performance and Risk | “replace two underground bus tie circuits within the Davis Substation” 69 kV |
| 2026-04-07 | TEAC Item 09 - DOM Supplemental Projects p. 7 |
Dominion Transmission Zone: Supplemental Equipment Material Condition, Performance and Risk | “Lines #275, #276 and #2037 provide service to Glebe, Crystal and Davis Substations” 230 kV |
| 2024-10-08 | TEAC Informational Only - DOM Local Plan submission of supplemental projects 2024 p. 93 |
Replace Davis TX#2 - DEV | “protection scheme update at Davis requires the addition of multiple external bushing CT’s” 230/69/13.2 kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.