Burlington Drive DP

Named in 1 PJM planning document for 1 project, on October 16, 2026.

Existingdescribed as
DOMzone
115 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Burlington Drive 115 kV DP – 3rd Feed - MEC
DOM-2026-0029
Under construction $0.010 M 10/30/2026 approximately 30 MW 2026-10-16
SRRTEP Mid-Atlantic

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 12/31/2026 → 10/30/2026 2026-08-13 2026-10-16

Every mention

DateDocumentProjectWhat the document says about it
2026-10-16 SRRTEP Mid-Atlantic
Item 05 - DOM Supplemental Projects Presentation p. 3
Burlington Drive 115 kV DP – 3rd Feed - MEC “Presently, Burlington Drive DP has a 115 kV transformer connected on Line #36.”
115 kV