Substation Scout

Huntingdon

Named in 3 PJM planning documents for 1 project, from September 9, 2025 to October 6, 2026.

Existingdescribed as
DLCOzone
138 kVkV as printed
3mentions

Also printed as: Huntingdon Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Monroeville, PA
DLC-2024-003 · s3928.1, s3928.2 and s3928.3
Not printed $46.3 M January 2029 250 MW 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - DLCO Local Plan Submission of the Supplemental Projects for 2026 p. 5
Monroeville, PA “Replace a 138 kV breaker at Huntingdon Substation”
138 kV
2026-09-21* SRRTEP Western
DLCO local plan submission of the supplemental projects for 2026 RTEP p. 5
Monroeville, PA “Replace a 138 kV breaker at Huntingdon Substation”
138 kV
2025-09-09 TEAC
Item 08 - DLCO Supplemental Project p. 4
Monroeville, PA “Replace a 138 kV breaker at Huntingdon Substation”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.