ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
DLCO Transmission Zone M-3 Process Pittsburgh, PA
DLC-2023-002 · S3356.1
Conceptual $0 1/31/2026 20 MW 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
DLCO local plan submission of the supplemental projects for 2024 RTEP p. 3
DLCO Transmission Zone M-3 Process Pittsburgh, PA “tapping the existing Brunot Island – Forbes 138 kV underground HPFF transmission line”
138 kV
2024-10-08 TEAC
Informational Only - DLCO Local Plan submission of supplemental project 2024 p. 3
DLCO Transmission Zone M-3 Process Pittsburgh, PA “tapping the existing Brunot Island – Forbes 138 kV underground HPFF transmission line”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this