Mitchell

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Existingdescribed as
DEOKzone
138/13 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Mitchell
DEOK-2023-003 · s3377.1
Engineering $1,870,984 12/4/2025 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
DEOK local plan submission of the supplemental projects for 2024 RTEP p. 8
Mitchell “capacity delivery through Mitchell substation.”
2024-10-08 TEAC
Informational Only - DEOK Local Plan submission of supplemental project 2024 p. 8
Mitchell “additional capacity delivery through Mitchell substation”
138/13 kV