Substation Scout

Urbana Substation

Named in 1 PJM planning document for 1 project, on July 8, 2025.

Existingdescribed as
DAYTONzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Dayton-2025-006 Not printed Not printed 6/2030 300 MW 2025-07-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-07-08 TEAC
Item 05 - Dayton Supplemental Projects p. 6
Dayton-2025-006 “vicinity of its Urbana Substation”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this