Y764-2

Named in 1 PJM planning document for 1 project, on October 6, 2026.

Existingdescribed as
COMEDzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Customer Expansion in Chicago
ComEd-2025-004 · s3823
Engineering $0M 12/31/27 52 MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named Y764 2 → STATION Y764 2 2026-10-06 Not reported
Substations named STATION Y764 2 → Y764 2 2025-06-13 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - ComEd Local Plan Submission of Supplemental Projects for 2026 p. 5
Customer Expansion in Chicago “complete double ring bus configuration at station Y764-2”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.