Substation Scout

Murray

Named in 2 PJM planning documents for 1 project, from May 16, 2025 to June 13, 2025.

Not stateddescribed as
ATSIzone
138 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Gates – Johnson 138 kV Line
ATSI-2025-015
Conceptual $1.96M 12/29/2028 Not printed 2025-06-13
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named GATES; JOHNSON; MURRAY → GATES; JOHNSON; JOHNSON SUBSTATIONS; MURRAY 2025-05-16 2025-06-13

Every mention

DateDocumentProjectWhat the document says about it
2025-06-13 SRRTEP Western
Item 05 - ATSI Supplemental Projects p. 7
Gates – Johnson 138 kV Line No role wording
138 kV
2025-05-16 SRRTEP Western
Item 05 - ATSI Supplemental Project p. 3
Gates – Johnson 138 kV Line No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this