Substation Scout

Harper

Named in 2 PJM planning documents for 2 projects, from March 14, 2025 to September 19, 2025.

Not stateddescribed as
ATSIzone
138 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Harper - West Akron 138 kV
ATSI-2025-002
Not printed Not printed Not printed 71 MW 2025-03-14
SRRTEP Western
Harper – West Akron 138 kV Line
ATSI-2025-023
Not printed Not printed Not printed Not printed 2025-09-19
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2025-09-19 SRRTEP Western
Item 03 - ATSI Supplemental Projects p. 3
Harper – West Akron 138 kV Line No role wording
138 kV
2025-03-14 SRRTEP Western
Item 05 - ATSI Supplemental Project p. 3
Harper - West Akron 138 kV No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.