Ford Brookpark Substation

Named in 2 PJM planning documents for 1 project, from September 18, 2026 to October 16, 2026.

Existingdescribed as
ATSIzone
138 kVkV as printed
2mentions

Also printed as: Ford Brookpark · Ford Brookpark Station

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New Customer Connection
ATSI-2026-061
Conceptual $13.78 M 11/29/2029 60 MW 2026-10-16
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 1/2/2029 → 11/29/2029 2026-09-18 2026-10-16
Substations named FORD BROOKPARK; FOWLES; FOX → AVON; DAWG POUND; EATON; FORD BROOKPARK; FOWLES; FOX; GM CLEVELAND PARMA; GROVEWOOD; JIM BROWN; NASA; PLEASANT VALLEY 2026-09-18 2026-10-16

Every mention

DateDocumentProjectWhat the document says about it
2026-10-16 SRRTEP Western
Item 02 - ATSI Supplemental Projects Presentation p. 13
New Customer Connection “The request is approximately 1 mile from Ford Brookpark Substation.”
138 kV
2026-09-18 SRRTEP Western
Item 02 - ATSI Supplemental Projects p. 5
New Customer Connection No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.