Evergreen Substation

Named in 5 PJM planning documents for 2 projects, from October 8, 2024 to October 6, 2026.

Existingdescribed as
ATSIzone
138 kVkV as printed
5mentions

Also printed as: Evergreen

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Newton Falls 138/69 kV Substation
ATSI-2022-031 · s3877.1
Not printed $51.52M 12/21/2028 69 MW 2026-10-06
TEAC
ATSI Transmission Zone M-3 Process Evergreen – Highland No. 3 138 kV Line Customer Connection
ATSI-2024-030 · s3456.1
Not printed $1.40 M 5/1/2025 17 MVA 2024-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named BRIDGE; EVERGREEN; FRANKLIN; IVANHOE; NEWTON FALLS; OHIO STAR FORGE; WHITMAN → BRIDGE; EVERGREEN; FRANKLIN; IVANHOE; NEWTON FALLS; NEWTON FALLS 138; OHIO STAR FORGE; WHITMAN 2026-10-06 Not reported
Substations named BRIDGE; EVERGREEN; FRANKLIN; GM LORDSTOWN; HANNA; IVANHOE; NEWTON FALLS; NEWTON FALLS 138; OHIO STAR FORGE; WHITMAN → BRIDGE; EVERGREEN; FRANKLIN; IVANHOE; NEWTON FALLS; OHIO STAR FORGE; WHITMAN 2025-12-12 2026-10-06

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2026 p. 29
Newton Falls 138/69 kV Substation “4.5 miles from Evergreen Substation”
2026-09-23* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2026 RTEP p. 29
Newton Falls 138/69 kV Substation “Remote end upgrades at Bridge, Ohio Star Forge, Ivanhoe, Evergreen, and Franklin substations.”
2026-09-08* SRRTEP Western
ATSI local plan submission of the supplemental projects for 2024 RTEP p. 89
ATSI Transmission Zone M-3 Process Evergreen – Highland No. 3 138 kV Line Customer Connection “Revise relay settings at Evergreen and Highland substations”
2025-12-12 SRRTEP Western
Item 13 - ATSI Supplemental Projects p. 8
Newton Falls 138/69 kV Substation “Remote end upgrades at Bridge, Ohio Star Forge, Ivanhoe, Evergreen, and Franklin substations.”
138 kV
2024-10-08 TEAC
Informational Only - ATSI Local Plan submission of supplemental project 2024 p. 90
ATSI Transmission Zone M-3 Process Evergreen – Highland No. 3 138 kV Line Customer Connection “Revise relay settings at Evergreen and Highland substations”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.