Bellevue
Named in 5 PJM planning documents for 3 projects, from March 14, 2025 to November 14, 2025.
Existingdescribed as
ATSIzone
69 kVkV as printed
5mentions
Also printed as: Bellevue Substation
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Bellevue-Groton 69 kV Line b3980.1 |
Not printed | $10.1M | 06/01/2030 | Not printed | 2025-11-14 SRRTEP Western |
| Bellevue-Groton 69 kV Line | Not printed | $10.1M | 06/01/2030 | Not printed | 2025-10-17 SRRTEP Western |
| Bellevue-Groton 69 kV Line ATSI-2023-013 · s3648 |
Not printed | $10.1M | 06/01/2026 | Not printed | 2025-10-08 TEAC |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-09-08* | SRRTEP Western ATSI local plan submission of the supplemental projects for 2025 RTEP p. 40 |
Bellevue-Groton 69 kV Line | “Bellevue Substation: Replace 6 manual switches with 2 GOAB switches, replace switch A98.” 69 kV |
| 2025-11-14 | SRRTEP Western Item 01 - SRRTEP West - Reliability Analysis Update p. 17 |
Bellevue-Groton 69 kV Line | “Bellevue Substation: • Replace (3) 69 kV disconnect switches” |
| 2025-10-17 | SRRTEP Western Item 01 - SRRTEP West - Reliability Analysis Update p. 11 |
Bellevue-Groton 69 kV Line | “Bellevue Substation:
• Replace (3) 69 kV disconnect switches” 69 kV |
| 2025-10-08 | TEAC Informational Only - ATSI Local Plan Submission of the Supplemental Projects for 2025 p. 40 |
Bellevue-Groton 69 kV Line | “Bellevue Substation: Replace 6 manual switches with 2 GOAB switches” 69 kV |
| 2025-03-14 | SRRTEP Western Item 05 - ATSI Supplemental Project p. 7 |
Bellevue-Groton 69 kV Line | “Bellevue Substation : Replace 6 manual switches with 2 GOAB switches, replace switch A98. Revise relay settings, upgrade ACSR connections” |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.