Dale Summit

Named in 3 PJM planning documents for 2 projects, from October 8, 2024 to July 7, 2026.

Not stateddescribed as
APSzone
230 kVkV as printed
3mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Milesburg 230 kV Substation
APS-2023-021 · s3483.1
Not printed $9.8M 12/17/2027 107.6 MW 2024-10-08
TEAC
Shingletown Substation
APS-2023-059, PN-2023-022
Conceptual $19.11M 06/25/2029 approximately 82.7 MW 2026-07-07
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
APS local plan submission of the supplemental projects for 2024 RTEP p. 124
Milesburg 230 kV Substation No role wording
230 kV
2026-07-07 TEAC
Item 06 - APS Supplemental Projects p. 8
Shingletown Substation No role wording
230 kV
2024-10-08 TEAC
Informational Only - APS Local Plan submission of supplemental project 2024 p. 124
Milesburg 230 kV Substation No role wording
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.