Named in 2 PJM planning documents for 1 project, on October 17, 2025.

Not stateddescribed as
AEPzone
69kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
East Tiffin, OH/Mousey Switch, OH
AEP-2025-OH024
Not printed Not printed Not printed Not printed 2025-10-17
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named EAST TIFFIN; MOUSEY → EAST TIFFIN; MOUSEY; WEST ROCKAWAY 2026-10-06 Not reported
Substations named NORTH CENTRAL CO OP; WEST ROCKAWAY → EAST TIFFIN; MOUSEY 2025-10-17 2025-11-14

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 38
East Tiffin, OH/Mousey Switch, OH No role wording
69kV
2025-10-17 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 4
East Tiffin, OH/Mousey Switch, OH No role wording
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.