Substation Scout

Ward Hollow 46 kV Station

Named in 3 PJM planning documents for 1 project, from March 14, 2025 to October 8, 2025.

Existingdescribed as
AEPzone
46 kVkV as printed
3mentions

Also printed as: Ward Hollow Station

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone M-3 Process Kanawha County, WV
AEP-2022-AP031, AEP-2023-AP022 · s3606.1-2
Conceptual $33.1 M 08/01/2027 Not printed 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2025 RTEP p. 24
AEP Transmission Zone M-3 Process Kanawha County, WV “The four 46kV transmission owned circuit breakers CB-D, CB-E, CB-B, and Bus Tie C are 72PM31-20 type, SF6 filled breakers”
46 kV
2025-10-08 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2025 p. 27
AEP Transmission Zone M-3 Process Kanawha County, WV “Replace existing 46 kV circuit breakers B, C and D”
46 kV
2025-03-14 SRRTEP Western
Item 08 - AEP Supplemental Projects p. 9
AEP Transmission Zone M-3 Process Kanawha County, WV “The four 46kV transmission owned circuit breakers CB-D, CB-E, CB-B, and Bus Tie C”
46 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this