Tom Watkins

Named in 2 PJM planning documents for 1 project, from April 15, 2026 to September 18, 2026.

Existingdescribed as
AEPzone
—kV as printed
2mentions

Also printed as: Tom Watkins Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Coleman - Stone 69 kV Line Rebuild
AEP-2026-AP003
Conceptual $55.44 M 08/01/2030 Not printed 2026-09-18
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named COLEMAN; STONE; TOM WATKINS → BARRENSHE; COLEMAN; PETER CREEK; PINSON; STONE; TOM WATKINS 2026-04-15 2026-09-18

Every mention

DateDocumentProjectWhat the document says about it
2026-09-18 SRRTEP Western
Item 03 - AEP Supplemental Projects p. 10
Coleman - Stone 69 kV Line Rebuild No role wording
2026-04-15 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 13
Coleman - Stone 69 kV Line Rebuild “customers served from Tom Watkins Substation”