Substation Scout

Prestonsburg

Named in 2 PJM planning documents for 2 projects, on May 16, 2025.

Existingdescribed as
AEPzone
46kVkV as printed
2mentions

Also printed as: Prestonsburg substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone: Baseline B3361 Scope Change
B3361
Not printed $63.6M 12/16/2027 Not printed 2025-05-16
SRRTEP Western
AEP Transmission Zone: Supplemental S2470.1-.7 Cancellation
AEP-2020-AP29 · S2470.1-.7
Cancelled $12.1 M 11/31/2023 Not printed 2025-05-16
SRRTEP Western

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$33.01M → $63.6M 2025-05-16 2025-05-16

Every mention

DateDocumentProjectWhat the document says about it
2025-05-16 SRRTEP Western
Item 01 - Reliability Analysis Update p. 3
AEP Transmission Zone: Baseline B3361 Scope Change No role wording
46kV
2025-05-16 SRRTEP Western
Item 03 - AEP Supplemental Projects p. 3
AEP Transmission Zone: Supplemental S2470.1-.7 Cancellation “Remote end work at Prestonsburg substation.”
46kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this