Substation Scout

North Wellsville

Named in 1 PJM planning document for 1 project, on September 18, 2026.

Not stateddescribed as
AEPzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
East Liverpool – North Wellsville
AEP-2026-OH035
Not printed Not printed Not printed Not printed 2026-09-18
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2026-09-18 SRRTEP Western
Item 03 - AEP Supplemental Projects p. 3
East Liverpool – North Wellsville No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.