North Baltimore

Named in 3 PJM planning documents for 1 project, from October 18, 2024 to October 8, 2025.

Existingdescribed as
AEPzone
34.5 kVkV as printed
3mentions

Also printed as: North Baltimore station

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
AEP Transmission Zone M-3 Process Wood County, Ohio
AEP-2019-OH052, AEP-2022-OH027 · s3641.1-15
Conceptual $80.204 M 11/30/2028 Not printed 2025-10-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named BELLARD; GREENSBURG; GYPSY LANE; NEW LIBERTY; NORTH BALTIMORE; POE ROAD; PORTAGE; PORTAGE SW; SANDRIDGE → BELLARD; GREENSBURG; GYPSY LANE; NEW LIBERTY; NORTH BALTIMORE; POE ROAD; PORTAGE; SANDRIDGE 2024-10-18 2025-10-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2025 RTEP p. 30
AEP Transmission Zone M-3 Process Wood County, Ohio “Portage is radially fed from AEP’s North Baltimore station”
34.5 kV
2025-10-08 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2025 p. 30
AEP Transmission Zone M-3 Process Wood County, Ohio “Portage is radially fed from AEP’s North Baltimore station”
34.5 kV
2024-10-18 SRRTEP Western
Item 06 - AEP Supplemental Projects p. 16
AEP Transmission Zone M-3 Process Wood County, Ohio “At North Baltimore 34.5 kV substation in order to accommodate the reconfiguration”
34.5 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.