NBY-7

Named in 3 PJM planning documents for 1 project, from January 17, 2025 to October 6, 2026.

Newdescribed as
AEPzone
138 kVkV as printed
3mentions

Described as new: “customer's new NBY-7 station” — source, page 108

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New Albany, OH
AEP-2023-OH068 · s4060.1
Engineering $0.6 M 8/1/2025 720 MW 2026-10-06
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 108
New Albany, OH “customer's new NBY-7 station”
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 108
New Albany, OH “extending it to the customer's new NBY-7 station”
138 kV
2025-01-17 SRRTEP Western
Item 04 - AEP Supplemental Projects p. 6
New Albany, OH “extending it to the customer's new NBY-7 station on their site”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.