Miller Switch Station

Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Existingdescribed as
AEPzone
—kV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Wayne County, WV
AEP-2023-AP005 · s3146.1-.3
Conceptual $7.8M 6/1/2024 12 MW 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 8
Wayne County, WV “Miller Switch Station will also be removed upon completion of the new line construction”
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 8
Wayne County, WV “Miller Switch Station will also be removed upon completion of the new line construction”