Substation Scout

Mammoth

Named in 2 PJM planning documents for 2 projects, from October 17, 2025 to November 14, 2025.

Not stateddescribed as
AEPzone
46 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Jarrett 138/46 kV Transformer & Hartland 46 kV Cap Adjustment
b3946.1
Not printed $0.2M 4/15/2030 Not printed 2025-11-14
SRRTEP Western
Jarrett 138/46 kV Transformer & Hartland 46 kV Cap Adjustment Not printed $0.2M 4/15/2030 Not printed 2025-10-17
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2025-11-14 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 28
Jarrett 138/46 kV Transformer & Hartland 46 kV Cap Adjustment No role wording
46 kV
2025-10-17 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 23
Jarrett 138/46 kV Transformer & Hartland 46 kV Cap Adjustment No role wording
46 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.