Named in 2 PJM planning documents for 2 projects, from October 17, 2025 to November 14, 2025.

Existingdescribed as
AEPzone
69 kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Hazard 69 kV R CB Replacement
b3974.1
Not printed $0.85M 6/1/2030 Not printed 2025-11-14
SRRTEP Western
Hazard 69 kV R CB Replacement Not printed $0.85M 6/1/2030 Not printed 2025-10-17
SRRTEP Western

Every mention

DateDocumentProjectWhat the document says about it
2025-11-14 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 97
Hazard 69 kV R CB Replacement “Replace overdutied Hazard 69 kV circuit breaker R”
69 kV
2025-10-17 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 92
Hazard 69 kV R CB Replacement “Hazard 69 kV R CB Replacement”
69 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.