Hatfield

Named in 4 PJM planning documents for 3 projects, from October 8, 2024 to November 14, 2025.

Not stateddescribed as
AEPzone
69kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Replace Johns Creek 69kV Capacitor Bank
b3948.1
Not printed $1.477 M 4/15/2030 Not printed 2025-11-14
SRRTEP Western
Replace Johns Creek 69kV Capacitor Bank Not printed $1.477 M 4/15/2030 Not printed 2025-10-17
SRRTEP Western
Pike County, KY
AEP-2022-AP034, AEP-2024-AP001 · s3303.1-.2
Engineering $1.74M 11/15/2024 20 MW 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Western
AEP local plan submission of the supplemental projects for 2024 RTEP p. 86
Pike County, KY No role wording
69kV
2025-11-14 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 32
Replace Johns Creek 69kV Capacitor Bank No role wording
2025-10-17 SRRTEP Western
Item 01 - SRRTEP West - Reliability Analysis Update p. 27
Replace Johns Creek 69kV Capacitor Bank No role wording
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 86
Pike County, KY No role wording
69kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.