Named in 1 PJM planning document for 1 project, on October 8, 2024.

Not stateddescribed as
AEPzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Taylor Station
AEP-2023-OH013 · s3301.1
Engineering $ 2.7M 3/28/2025 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2024-10-08 TEAC
Informational Only - AEP Local Plan submission of supplemental projects 2024 p. 82
Taylor Station No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.