Named in 3 PJM planning documents for 1 project, from September 19, 2025 to October 6, 2026.

Newdescribed as
AEPzone
—kV as printed
3mentions

Described as new: “Install a new tap point” — source, page 19

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Aloe Vera SW, WV
AEP-2025-AP003 · s3827.1
Engineering 0 03/05/2026 7MW 2026-10-06
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date March 2026 → 03/05/2026 2025-03-14 2025-09-19
Substations named ALOE VERA SW; BAILEYSVILLE; LOGAN; SWITCHBACK; TRAIL FORK → ALOE VERA SW; BAILEYSVILLE; LOGAN; SWITCHBACK; TRAIL FORK STATIONS 2026-10-06 Not reported

Every mention

DateDocumentProjectWhat the document says about it
2026-10-07* SRRTEP Western
AEP local plan submission of the supplemental projects for 2026 RTEP p. 19
Aloe Vera SW, WV “Install a new tap point”
2026-10-06 TEAC
Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 19
Aloe Vera SW, WV “Install a new tap point on the existing Logan - Switchback 138 kV line”
2025-09-19 SRRTEP Western
Item 06 - AEP Supplemental Projects p. 8
Aloe Vera SW, WV “Install a new tap point”