Abert
Named in 4 PJM planning documents for 1 project, from October 17, 2025 to October 6, 2026.
Existingdescribed as
AEPzone
69 kVkV as printed
4mentions
Also printed as: Abert Station
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| Abert, VA AEP-2025-AP007 · s3841.1 |
Conceptual | $3.4 M | 11/16/2029 | Not printed | 2026-10-06 TEAC |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-10-07* | SRRTEP Western AEP local plan submission of the supplemental projects for 2026 RTEP p. 43 |
Abert, VA | “Station will be expanded” 69 kV |
| 2026-10-06 | TEAC Informational Only - AEP Local Plan Submission of the Supplemental Projects for 2026 p. 43 |
Abert, VA | “Station will be expanded to accommodate the new location of the circuit switcher and capacitor bank” 69 kV |
| 2025-11-14 | SRRTEP Western Item 03 - AEP Supplemental Projects p. 16 |
Abert, VA | “Station will be expanded to accommodate the new location” 69 kV |
| 2025-10-17 | SRRTEP Western Item 04 - AEP Supplemental Projects p. 5 |
Abert, VA | “Abert Station: 69 kV Cap Bank Circuit Switcher AA is a 2030-69 type, SF6 filled switcher” |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation".
- role is "new" only where a cited document phrase describes the substation as new or describes constructing it, "existing" where a phrase describes work at it, otherwise "unknown".
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.