Named in 2 PJM planning documents for 1 project, on October 8, 2024.

Not stateddescribed as
ACEzone
—kV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
ACE-2022-009 Engineering $18M 1/31/2028 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
ACE local plan submission for 2024 RTEP p. 5
ACE-2022-009 No role wording
2024-10-08 TEAC
Informational Only - ACE Local Plan submission of supplemental project 2024 p. 5
ACE-2022-009 No role wording

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.