Substation Scout

Lamb

Named in 1 PJM planning document for 1 project, on Not reported.

Existingdescribed as
ACEzone
69/12 kVkV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
New Transformer at Lamb Substation
ACE-2023-002 · s3181.1
Conceptual $2.5 M 6/30/2027 Not printed 2026-09-08*
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
ACE local plan submission for 2024 RTEP p. 11
New Transformer at Lamb Substation “Install a new 69/12 kV 40 MVA transformer at Lamb substation”
69/12 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.