Chaves, NM interconnection queue

14 active projects totaling 2,098.7 MW in the SPP queue, plus 25 with terminal status (shown grayed).

14active projects
2,098.7active MW
39total filed
Queue IDProjectkVMWResourceStatus
GEN-2024-198 Not reported 345 500 Wind Withdrawn
GEN-2024-199 Not reported 345 500 Wind Withdrawn
GEN-2022-014 Not reported 230 400 Solar Withdrawn
ERAS-2025-030 Not reported 230 350 Hybrid Active
GEN-2024-279 Not reported 230 350 Hybrid Withdrawn
GEN-2015-009 Not reported 230 300 Wind Withdrawn
GEN-2019-008 Not reported 230 300 Solar Withdrawn
GEN-2022-022 Not reported 230 300 Solar Withdrawn
GEN-2024-200 Not reported 345 300 Hybrid Withdrawn
GEN-2008-022 Not reported 345 299.7 Wind Operational
GEN-2003-018 Not reported n/r 298.5 Wind Withdrawn
GEN-2022-159 Not reported 345 280 Wind Withdrawn
GEN-2022-160 Not reported 345 280 Wind Withdrawn
GEN-2024-201 Not reported 345 260 Hybrid Withdrawn
GEN-2024-271 Not reported 230 250 Hybrid Active
GEN-2024-311 Not reported 230 225 Solar Active
GEN-2022-033 Not reported 230 200 Hybrid Withdrawn
GEN-2024-186 Not reported 115 199 Battery Active
GEN-2022-023 Not reported 230 175 Battery Withdrawn
GEN-2005-011 Not reported n/r 160 Wind Withdrawn
GEN-2024-324 Not reported 115 160 Battery Active
GEN-2024-203 Not reported 230 150 Battery Withdrawn
GEN-2024-325 Not reported 115 150 Battery Active
GEN-2014-046 Not reported 115 125.4 Solar Withdrawn
GEN-2001-033 Not reported 230 120 Wind Operational
GEN-2014-063 Not reported 230 120 Wind Withdrawn
GEN-2014-048 Not reported 115 110 Solar Withdrawn
GEN-2024-310 Not reported 230 75 Battery Active
GEN-2014-033 Not reported 115 70 Solar Operational
GEN-2014-034 Not reported 115 70 Solar Operational
GEN-2008-009 Not reported 230 60 Wind Withdrawn
GEN-2021-083 Not reported 69 50 Hybrid Withdrawn
GEN-2025-SR27 Not reported 115 50 Battery Active
GEN-2025-SR32 Not reported 115 50 Battery Active
GEN-2008-102 Not reported n/r 34.2 Solar Withdrawn
GEN-2016-069 Not reported 115 31.4 Solar Withdrawn
GEN-2014-035 Not reported 115 30 Solar Operational
GEN-2010-020 Not reported 69 20 Solar Withdrawn
GEN-2010-058 Not reported 115 20 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with SPP before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first